The full cost of buying a home in Bangalore.
The price on the brochure is not what you pay. Here is everything that gets added, with a worked example, so your budget holds on the day you sign.
Updated November 2026. Rates change; confirm with your advisor, bank and the Karnataka Kaveri portal before you pay.
1. Taxes and government charges
| Charge | Rate | Who it applies to |
|---|---|---|
| GST | 5% of the agreement value | Under-construction homes. No GST on ready homes that already have an Occupancy Certificate (OC). |
| GST, affordable homes | 1% | Under-construction homes up to ₹45 L with carpet area up to 60 sq m in Bangalore. |
| Stamp duty | 5% for homes above ₹45 L, plus cess and surcharge | Everyone, paid when the sale deed is registered. |
| Registration fee | 2% of the property value | Everyone. Karnataka raised this from 1% to 2% from 31 August 2025. |
| TDS | 1% of the price | Homes priced at ₹50 L or more. Not an extra cost: you deduct it from what you pay the builder and deposit it with the tax department (Form 26QB). |
Stamp duty and registration are charged on the higher of the sale price and the government guidance value.
2. Charges from the builder
These vary by project. Ask for each one in writing on the cost sheet before you book.
- Floor rise and preferred location charges (PLC)A higher floor, a corner, a park view or east facing can add to the price per sq ft.
- Car parkingOften charged per slot, sometimes included. Check how many slots and whether covered.
- Clubhouse membershipA one-time charge in some projects.
- Maintenance advance and corpus fundUsually collected at handover, often for 1 to 2 years of maintenance plus a one-time corpus.
- Electricity, water and other connectionsDeposits for BESCOM, water and gas lines, often passed on at actuals.
3. Loan and paperwork costs
- Loan processing feeCharged by the bank, usually a small percentage of the loan. Often waived in offers.
- Legal and documentationAn independent title check, agreement drafting and the khata transfer after registration.
- Home insuranceOften required by the lender.
Worked example: a ₹1 Cr under-construction home
| Item | Amount |
|---|---|
| Agreement value | ₹1,00,00,000 |
| GST at 5% | ₹5,00,000 |
| Stamp duty at 5% | ₹5,00,000 |
| Registration fee at 2% | ₹2,00,000 |
| Total before builder charges | ₹1,12,00,000 |
Cess and surcharge on stamp duty, floor rise, parking, club and maintenance charges come on top. TDS of ₹1,00,000 is deducted from your payments to the builder, so it does not add to the total. Illustrative only.
Advisor's tip: budget 12 to 15% above the agreement value for an under-construction home, and about 7 to 8% above for a ready home with OC. Ask for the builder's full cost sheet before comparing two projects; base prices alone mislead.